Shear Capacity Checks_Normal Force
Shear Capacity Checks_Normal Force
I am checking an RC joint shear report. I am realizing that the normal force of the column above the joint at Collapse Prevention LS is nearly 90kN, while the one reported in the report generated by SB says that the normal force is nearly 70kN. I am conducting the joint shear check as per NTC-18. Could you please shed some light on what can the source of this mismatching?
Re: Shear Capacity Checks_Normal Force
Dear E.Veliu,
Indeed, there is a bug in this check. Thank you for reporting it. A new release will be published with this bug fixed within next week.
Indeed, there is a bug in this check. Thank you for reporting it. A new release will be published with this bug fixed within next week.
Zoi Gronti
Seismosoft Srl.